Church Center Construction

March 27th 2017

HVAC, MEP, false ceiling, window fixing etc

IMAG1724.JPG

______________________________________________________________________

March 15th 2017

External works, interlock, marble stairs, AC ducting, false ceiling, MEP work

IMAG0987.JPG

______________________________________________________________________

February 25th 2017

waterproofing on the roof, painting, AC ducting, false ceiling work

IMAG9862.JPG

______________________________________________________________________

February 5th 2017

IMAG8615.JPG

_______________________________________________________________________

Jan 20th 2017

roof paneling 75% complete, tile work on going, AC ducting work on going, exterior plaster

IMAG7614.JPG

________________________________________________________________________

January 10th 2017

roof paneling 50% complete, tile work, AC ducting work on going

IMAG7005.JPG

________________________________________________________________________

December 26th 2016

steel roof structure 80% complete, boundary wall work 60%, MEP work ongoing

IMAG6043.JPG

 

______________________________________________________________________

December 10th 2016

steel roof structure 30% complete, boundary wall work 25%

IMAG5047.JPG

_______________________________________________________________________

November 28th 2016

Plasterwork, MEP work, boundary wall work underway

IMAG4292.JPG

_______________________________________________________________________

November 14th 2016

100% of blockwork is complete. Plaster work underway

IMAG3425.JPG

______________________________________________________________________

October 31st 2016

Roof column casting and 75% blockwork complete

IMAG2581.JPG

______________________________________________________________________

October 17th 2016

Removing scaffolding under roof slab and preparing 1st floor beam.

IMAG1703.JPG

______________________________________________________________________

October 4th 2016

Casting of roof columns and block work on roof parapet.

IMAG0916.JPG

______________________________________________________________________

September 25th 2016

Casting of 430 sqm of concrete for the roof slab. 50 trucks of concrete were poured into the slab.

IMAG0370.JPG

 

______________________________________________________________________

September 19th 2016

95% of formwork and 75% of steel work for roof slab complete.

IMAG9971.JPG

_____________________________________________________________________

September 10th 2016

80% of formwork and 50% of steel work  for roof slab complete.

 IMAG9418.JPG

 _____________________________________________________________________

August 30th 2016

60% of formwork for roof slab complete.

IMAG8738.JPG

_____________________________________________________________________

August 15th 2016

100% of groundfloor columns complete.

IMAG7804.JPG

____________________________________________________________________

August 5th 2016

70% of groundfloor columns complete.

IMAG7182.JPG

____________________________________________________________________

July 25th 2016

ground floor columns 35% complete. Steelbending & shuttering work on going.

IMAG6515.JPG

_____________________________________________________________________

July 20th 2016

column work underway. concrete floor slab for children's area and offices is cast.

IMAG6233.JPG

_____________________________________________________________________

July 10th 2016

casting of groundfloor concrete slab in chapel and foyer area. Backfilling 70% complete.

IMAG5624.JPG

____________________________________________________________________

July 2nd 2016

Backfilling 50% complete. watertank footing cast and transformer room tiebeam cast.

IMAG5089.JPG

____________________________________________________________________

June 27th 2016

Backfilling under tiebeam level 35% complete

IMAG4789.JPG

____________________________________________________________________

June 20th 2016

Deshuttering, bitumen waterproofing and backfilling under tiebeam level.

IMAG4354.JPG

_____________________________________________________________________

June 11th 2016

Casting of 130 m3 of concrete for Tiebeam and outer neck column.

IMAG3826.JPG

___________________________________________________________________

June 6th 2016

Tiebeam steelbending complete. Formwork for Tiebeam casting 90% complete.

IMAG3488.JPG

___________________________________________________________________

May 30th 2016

80% of neck column casting complete. Blockwork under tiebeam at 100% completion. Tiebeam steelbending complete. Formwork for Tiebeam casting 60% complete

IMAG3056.JPG

___________________________________________________________________

May 23rd 2016

80% of neck column casting complete. Blockwork under tiebeam at 100% completion. Tiebeam steelbending complete. Tiebeam casting on 30th May 2016

IMAG2631.JPG

____________________________________________________________________

May 14th 2016

80% of neck column casting complete. Blockwork under tiebeam at 80% completion. Tiebeam steelbending underway.

IMAG2072.JPG

___________________________________________________________________

May 7th 2016

40% of neck column casting underway. Blockwork under tiebeam at 40% completion

IMAG1652.JPG

____________________________________________________________________

May 2nd 2016

Concrete curing of footings, neck column formwork and blockwork under tiebeam.

IMAG1331.JPG

__________________________________________________________________

April 27th 2016

Casting of 320m3 of concrete for RCC footings. Two concrete pumps were employed and aprox. 40 concrete trucks came to site.

IMAG1030.JPG

_____________________________________________________________________

April 18th 2016

Formwork & steelbending at 60% completion. Neckcolumn work beginning at the northwest end of the site.

IMAG0471.JPG

_____________________________________________________________________

April 11th 2016

Formwork and steelbending to make reinforced cages for the foundation footings.

IMAG0045.JPG